Minutes of Site Inspection
LOCATION: Dominick Pagano Application #21-08
241 Ethan Allen Highway
DATE: June 7, 2021
TIME: 5:30 PM
PRESENT:
COMMISSION
D. Pattee
S. Green
B. Hill
C. Matzke
W. Perlman
S. Robinson
APPLICANT
C. Lowenstein
M. Kaufman
The Commission began the inspection at the south end parking lot and proceeded to the west side of the property. The location of the proposed retaining wall was noted as was the area next to the Norwalk River. The proposed building expansion was pointed out by C. Lowenstein. The Commission moved to the north end of the building and observed the existing catch basin that will be upgraded to capture sediment and remove hydrocarbon chemicals prior to discharge. The Commission completed the site inspection at the south end of the building to observe the locations of the proposed storm water drainage treatment system.
The site inspection ended at 6:00 pm.
Submitted by: David Pattee